Project Progress Meeting (PM2) IPM-4-Citrus has taken place on 26th and 27th September 2019 at JKI (Darmstadt, Germany) with 11 persons. Nine partners were represented (JKI, LISBP, USJ, MEDIS, CBS, BIPCA) or by visio-conference (IPT, BIYANS, CTA). WSU and TWB were missing but state points have been previously done with each partner.

PM2 was divided in 2 days as described by working program including (i) administrative and scientific progress of the project and (ii) exchange and evaluation of secondments realised, cancelled, maintained but delayed, redeployed or new request. The main stakes were to define the next and/or new secondments (T0+30/T0+48months) highlighted by scientific and technical inputs in order to focus on achievable goals and make the best of the time left on conducting the project / strengthening actions. Following this PM, The consortium has submitted to the project PO, its final modifications (flushing, additional secondments) for validation and acceptance.

Day 1: Thursday 26th September (PM2):

9.00 – 9.30    Welcome Coffee & Welcome foreword

– by Dietrich Stephan, Work Package 3 responsible

– by Project Coordinator – Dr Luc FILLAUDEAU (INSA, LISBP)

9.30 – 12.30: W.P Reporting *

WP 1 – Management (Luc FILLAUDEAU, Souad ROUIS, Jerome CUBERO)

WP 5 – Networking & Outreach – (Jerome CUBERO)

WP 2 – Bioprocess (Souad ROUIS)

WP 3 – Biotech (Dietrich STEPHAN)

WP 4 – Transfer (Sara FALVO, Bernadetta MARESCA)

14.00 – 16.30: Secondment planning and implementation – with Visio conference with IPT, BIYANS and CTA

16.30 – 17.00: Wrap-up and conclusions of 1st day meeting

Day 2: Friday 27th September (PM2):

9.00 – 10.30: Secondment planning and implementation / Visio conference with IPT, BIYANS and BIPCA  Final validation before proposal diffusion to PO

10.30 – 12.30: Scientific & technical discussion related with formulation and DSP.

Next “IPM4Citrus”: identification of next EC calls (What’s next & Call for action).

14.00 – 16.00: Presentation of agricultural research in Germany, of JKI facilities and Lab tour of JKI (Darmstadt)

16.00 – 17.00: Wrap up & Conclusion WP3 and WP4 activities will be strengthened with secondments reflushing (market strategy and industry transfer to be comforted). The participation to IDB 2019, a scientific event, held in Tunisia in December 2019 has been considered of high interest for the project consortium (Consortium meeting, communication).